For small plastic parts (envelope ≤70×70×70 mm), a single-cavity steel mould built in China typically runs USD 1,200–2,500; a two-cavity tool USD 1,900–3,500; tools with slides or unscrewing cores USD 3,000–6,000. Quotes come back in 2 business days, T1 parts in 25–45 days, and the tool belongs to you.
Price bands by tool type
| Tool type | Typical cavities | Indicative price (USD) | Drawing to T1 | Best for |
|---|---|---|---|---|
| Single cavity, 2-plate | 1 | 1,200 – 2,500 | 25–30 days | Pilot runs, design validation, under 50k pcs/yr |
| 2–4 cavity, 2-plate | 2 – 4 | 1,900 – 3,500 | 30–35 days | Steady production where part cost matters |
| With slides (side action) | 1 – 2 | 3,000 – 5,000 | 35–45 days | Parts with side holes, clips or undercuts |
| Unscrewing core | 1 – 2 | 4,000 – 6,000 | 40–45 days | Caps, threaded fittings, screw closures |
| Hot runner, multi-cavity | 4 – 8 | 6,000 – 12,000 | 40–50 days | Over 200k pcs/yr, lowest possible unit price |
Bands are 2026 transaction prices from our own tool room in Shandong, including mould base, steel, machining, trial and crated packing. Freight, duty and part price are not included.
Why the same drawing gets quotes 3× apart
01Steel grade and mould base
Pre-hardened 718H versus hardened S136, standard versus in-house mould base — that alone can swing 40%. We machine the base and standard parts ourselves and cut pockets after hardening, built for 300,000 shots.
02Cavity count and layout
Two cavities do not double the price — base, runner and ejection are shared, so it is usually +30–50%. What really drops is your part price, once the tool fits a bigger press.
03Slides, lifters and unscrewing
Every side action is a separate mechanism and is costed in fitter days. One slide adds USD 400–800, an unscrewing unit USD 1,200–2,000, and 5–10 days of lead time each.
04Surface and tolerance
Standard texture (VDI 3400) is included; mirror polish, high-gloss ABS cosmetics and ±0.02 mm fits are extra operations. Say it in the RFQ, not after T1.
How the part price is built
Part price = material + press time + scrap. Take a 25 g PP part in a 2-cavity tool on a 45-second cycle: 160 parts/hour, small-tonnage press time at USD 12–18/hour gives USD 0.08–0.11 of machine cost; PP at about USD 1.4/kg adds USD 0.035; with runner regrind and packing the FOB Qingdao price lands at USD 0.12–0.18.
Material
Part weight × resin price, plus 3–8% runner loss. PP and ABS are cheapest; PA, PC and TPE step up from there.
Press time
Cycle ÷ cavities × hourly machine rate. Wall thickness drives the cycle: 1.5 mm walls run 20–30 s, 3 mm walls need 45–60 s.
MOQ and batch size
Normal batches start at 500 pcs (smaller trial runs are quoted separately); changeover and setting costs are spread across the batch. Above 5,000 pcs the unit price usually drops another 10–15%.
Questions buyers actually ask
- How long does a mould take?
- Twenty-five to forty-five days from drawing approval to T1: 25–30 for a simple 2-plate tool, 35–45 with slides, 40–50 for hot-runner multi-cavity. After T1 we rework to your comments and usually ship T2 samples in 3–7 days.
- Who owns the mould?
- You do. Once the tool is paid for it is your property and you can move it at any time; we hand over the tool drawings, cooling layout and a spare-parts list. It is written into the quotation, not just promised.
- Can I run a small trial batch first?
- Yes. Normal batches start at 500 pcs and smaller trials are quoted separately; T1 samples ship first so you can check fit and cosmetics before the run. For low annual volumes, a single-cavity tool plus small batches is the cheapest route.
- What do you need to quote?
- A 3D file (STEP / IGES / X_T) or a 2D drawing; if you only have a sample, send it or six photos with caliper dimensions. Add material, annual volume, surface requirement and target price — the quote plus DFM notes comes back in 2 business days.
- How long does the tool last, and who fixes it?
- Designed for 300,000 shots, with cavities cut after hardening. Normal wear — ejector pins, gates, slides — is repaired free while the tool is with us; crash damage or design changes are quoted separately.
- What about freight and duty?
- FOB Qingdao by default — Weifang to Qingdao port is about 2 hours by truck. EXW or CIF also work with your forwarder. Duty is payable at destination under your HS code; we supply the full declaration pack.
Send the drawing — price in two days
Email info@yichaomold.cn or WhatsApp +86 183 6966 7875 with the 3D file, material and annual volume. You get the price, DFM notes and a stage-by-stage tool schedule.